Andromeda Metals' Great White Project - Kaolin

The Great White Project (GWP) is located on the Eyre Peninsula in South Australia and is a high-grade kaolin project with a 28 year mine-life.

The GWP is based on the Great White deposit which contains high-quality kaolin that, when refined through on-site wet processing, produces kaolin products that can be used in high-end applications in the ceramics and concrete markets.

The high-quality refined kaolin products from the GWP have been validated by global ceramics industry experts and customers.

Future upside opportunities for GWP include additional expansion and new, high-value added products, such as the production of the Critical Mineral high-purity alumina (HPA).

The GWP is planned to be developed over stages to produce refined kaolin products of up to 330,000 tonnes per annum (tpa), as follows:
• Stage 1A+ 100 ktpa of production
• Stage 1B an additional 110 ktpa of production
• Stage 2 an additional 120 ktpa of production.

The GWP has been largely de-risked and is ready to develop, with:
• All key permits in place for construction to commence
• Feasibility studies completed; and
• Major offtakes finalised for the initial stage of production (Stage 1A+).

Andromeda aims to secure A$90 million in funding, plus financing costs, interest and cash reserves, to support a final investment decision for Stage 1A+, which includes A$84M in CAPEX.

Of this, credit approval has been received from Merricks Capital for a A$75 million debt facility with a process underway to secure the remaining balance of funding required.

Investment sought: A$90 million, excluding financing costs, interest and cash reserves, which includes A$84M in CAPEX for Stage 1A+.

Investment opportunity

Direct or project-level investment – as part of funding required to support a final investment decision for Stage 1A+.

Gallery images

Investor information

Documents

Project status update

Project status: Definitive Feasibility Studies completed.
Government Approval status: Mine approved to commence constructions.
Scheduled start, subject to a final investment being made, of:
• Construction: 2H 2025
• Mining operations: 2H 2026
Current expected mine life: 28 years

Project dependencies

Pending government approval for mining proposal.

Technology utilised

Free-dig mining and hydro-mechanical mineral processing using conventional equipment.

Financial information

Investment sought: A$90M

Project highlights

  • World class resource of rare and valuable mineral • All key approvals received to commence development • Simple mining with low strip ratio • All Feasibility Studies required completed • Low capex hurdle • Staged development in-line with anticipated growth in market demand

Key organisations

  • Andromeda Metals Ltd

Project timelines

Expected start date
-

Expected end date
-

Funding round finish date
-

Website

andromet.com.au/project/great-white-kaolin-project

Location

View on AgInsight interactive information and mapping portal